|

One of the logistical challenges that faced the Allies
during the planning of the 1944 D-Day Landings was the whole question of a
suitable port on the European Coast that was big enough to take large supply
vessels and equipment and could be captured in tact.
A revolutionary solution to this riddle was found in
the so-called Mulberry Harbours. The early lessons in respect of assault
landings were learnt at the Training Centre at Inveraray on Loch Fyne and as
early as May 1942 the plans for floating harbours received the enthusiastic
backing of Prime Minister Winston Churchill. “They must float up and down
with the tide”, he wrote. “The anchor problem must be mastered. Let me have
the best solution worked out. Don’t argue the matter. The difficulties will
argue for themselves”.
Trials of several prototypes took place at Garlieston
in Wigtonshire in South West Scotland. The results of these trials were the
two great Mulberry Harbours, Mulberry A and Mulberry B. These consisted of
huge concrete caissons forming breakwaters, enclosing an area of about
1300acres, two miles long and a mile out to sea, within which steel "spud”
pierheads were connected to the shore by piers ¾ of a mile long. Not only
had the structures to be built but they also had to be towed to assembly
points on the south coast and then taken across the English Channel to the
beaches of Normandy. Mulberrys were one of the greatest feats of engineering
of the Second World War.
The equipment was manned by two specially raised Port
Floating Equipment Companies of the Royal Engineers (969th and
970th) and by US Navy Construction Companies known as Seabees.
The Royal Engineers trained at Garlieston and amongst them were a number of
Scots including Glasgow Academy and Glasgow University graduate R J P Cowan.
As newly formed companies however many RE units had taken the opportunity to
transfer out some of their more problematic soldiers and a number of men of
the PFE Companies created havoc in rural Wigtonshire, including the burning
of their billet Glasserton House.
Construction of the huge concrete and steel structures
was carried out in several places in the UK including Henry Robb’s
Shipbuilding Yard at Leith where the design of the units and the
co-ordination of the work was under the supervision of Alexander Findlay &
Company of Motherwell. Finishing work was done at Newhaven alongside the
fish quay. A total of thirteen pierheads and sixteen large pontoons for the
Mulberry Harbours were built at Leith. Other construction took place at
Cairnryan on the west coast.
Having been towed south, on D-Day + 2, the 8th
of June 1944 the first component parts arrived at the Normandy Landing
beaches and construction began. In the early hours of June 14th,
after six days of non-stop work, the first supplies came ashore from the
harbours and by D+10 2000 tons of stores and ammunition a day were being
unloaded over the piers. |